DELAY IN CONSTRUCTION WORK

Finally, JP Nagar underpass nears completion

After a delay of nearly 1.5 years, the underpass at the intersection of JP Nagar's 15th cross Ring Road and 24th Main may be completed in a month's time. Still, both the BBMP and the area MLA are not categorical about D-day.

By Vaishnavi Vittal


Nearly two and a half years after work began, there may finally be light at the tunnel, or in this case, an underpass. Construction on the JP Nagar 15th cross Ring Road in south Bengaluru is scheduled to be completed by the third week of September.

Signs of completion have emerged as work entered the 30th month. Pic: Venkatesan Perumal.

Highly placed sources in the BBMP have confirmed this to Citizen Matters but refused to comment on when the underpass itself will be inaugurated thereafter.

The BBMP official says that work left to be completed includes painting, lighting, laying of pavement quality concrete, and work on the service roads. A worker at the construction site says that Rs 10 lakhs worth of work, of the Rs 23 crore project, is left to be completed.

Citizen Matters spoke to Jayanagar constituency MLA B N Vijaykumar who says the underpass will be ready in a month's time. "This is what the contractor told. We cannot depend on them", Vijaykumar says, adding that an inauguration date cannot be fixed unless the work is completed.

Underpass at Ring Road-Puttenahalli junction

Date of commencement of work: March 2008

Scheduled to have been completed in 10 months

Project Cost: Rs.23 crores (JnNURM funds)

Name of agency: Engineering Projects (India) Ltd

Road width: 15 metres (4-lane)

Height: 5.5 metres

Delayed work inconveniences residents and traders

Started in March 2008, work on this underpass has stretched on for over two years now. Sources in the BBMP say that the project has been delayed because of the agency carrying out the work - Engineering Projects (India) Ltd. "They have not used funds properly, they have not worked on proper shifts", says the BBMP source, adding, "If they don't finish the work, we will terminate the contract and get it done from a third party."

Interestingly, Transport Minister R Ashoka inaugurated the overbridge on 24th Main Road towards Puttenahalli and Jambusavari Dinne on May 2nd this year.  The 15th Cross underpass goes below this bridge, where it intersects 24th Main Road.

A project that was meant to be completed in ten months, will enter its 30th month in September this year. During this period, residents and businesses near the construction site have paid a steep price. Several commercial establishments were forced close shop because of the drop in footfalls.

In September 2009 Citizen Matters reported on this. At that time, BBMP's Engineer-in-Chief A K Gopalaswamy had said people would have to be "patient". He had also said that the underpass would be ready in a "few months."

Suresh Rangaswamy, resident of JP Nagar. Pic: Vaishnavi Vittal.

Residents of the area have also had a hard time, with traffic being diverted to the once-quiet residential neighbourhoods. Suresh Rangaswamy, who lives on 14th cross 25th main in JP Nagar I Phase, says the project has resulted in a lot of chaos in the area, resulting in accidents as well.

Thirty-four year old Rangaswamy says the area has also seen a rise in the number of thefts in the area. "So many strangers are passing by. My wife's bike was stolen. We found it after about three months", he explains.

The recent rains have also made life hell for pedestrians near the site, thanks to the slush-filled potholes.

Rangaswamy feels that projects like these are started without thinking of public safety and lack of coordination between authorities. "Any developmental work within the city inconveniences the citizens, when it stretches beyond a point."

References       


Update       



See articles on

SocialTwist Tell-a-Friend

post a comment
Note: Solicitation and commercial posts not allowed.
See Comments policy and disclaimer


2 Comments         
[08 PM, 30 Aug 2010] Deepa Mohan

This is another reason why we hate the thought of having more road work done; we know that the misery will prolong for long beyond the due date, with no accountability on the part of the contractors or BBMP, who have taken 30 months to even think about changing the contractor, for a scheduled time of 10 months. The public's suffering is the last thing on these people's minds and we are told to "be patient". What are we paying taxes for, we wonder.

[06 PM, 29 Nov 2010] dr.chandra sekhar

could we get a recent status report on this project by Ms.vittal


Please login to post a comment. If you do not have a login, please register to get one. It's simple process - takes less than a minute.

You can post comments without registering, and they will appear after approval, usually within 12 hours. We encourage you to login - then your comments appear immediately!

Post as un-registered user

Login:

Email id:

Password:

Forgot password?

Remember me on this computer.

Register:

Email id:

I have read and I agree to the Terms and Conditions and the Privacy Policy

Please check your e-mail in a few minutes for a mail with instructions to activate your account.
Note: If you do not recieve the confirmation email within a few minutes of registering, check your spam folder. Some email tools may mistakenly treat legitimate email from a new email address as spam.



comment

feedback
feedback


Related to this article
JP NAGAR RING ROAD UNDERPASS
Underpass work shows no progress
GREEN LIGHT AHEAD FOR COMMUTER RAIL?
GoK pushing SW Railway for local trains within Bengaluru
BBMP SPENDS CRORES ON PARKS
The great Koramangala park robbery
DENOTIFIED LAND TAKEN OVER
BTM Society fights back, stops land grab
HOW CITIZENS STOPPED A BDA PROJECT
Citizens' alternative to BDA's grade separator plan
AUTO PREPAID COUNTER RACKET
Mini racket at auto prepaid counters

More..

Our Writers

Catch up on latest stories from over two dozen writers!

See our complete list of authors to spot your favourite!

Looking to advertise on our website?
Contact us for more details.
To advertise, contact us
Call: 80-4173-7584 * 9844 22 8666